Route Adams Temporary Road Repairs

Route Adams: road repairs and temporary speed reduction

Last summer, a new underground gallery was constructed beneath Route Adams as part of the Building 777 project. Unfortunately, the road surface adjacent to the new gallery has settled more than expected after the particularly dry summer. This has resulted in deformation and unevenness in several locations along the road.

Initial repair works were carried out in September. As the settlement has continued and some deformations have again exceeded acceptable tolerances, further repairs are required to maintain the road in a safe condition.

The next intervention is currently planned for Wednesday 4th and Thursday 5th November. The works will be carried out on one side of the road at a time, with traffic managed by a traffic marshal. A full closure of Route Adams will therefore not be necessary, although some short delays may occur.

We sincerely apologise for the inconvenience caused, particularly as this issue has unfortunately recurred within such a short period of time. We appreciate the frustration and safety concerns this may cause for those regularly using the road.

In parallel with these temporary safety measures, we are continuing to investigate the underlying cause of the settlement so that we can ensure the problem is fully resolved in the future. As part of this work, we are currently studying a potential solution involving reinforced concrete slabs on either side of the underground gallery to reduce the differential settlement observed between the gallery and the surrounding road.

Thank you for your patience and understanding while we work towards a long-term solution.

Temporary speed reduction to 30 km/h

As further settlement may still occur, and given the significant amount of construction traffic currently using Route Adams, the speed limit will be reduced to 30 km/h.

This speed reduction also anticipates the future configuration of the area following completion of the Building 777 project, with a more pedestrian-friendly environment around Buildings 777, 866, 864 and 867.

The measure therefore aims not only to improve the safety of road users and construction workers during the ongoing works, but also to support the longer-term objective of creating a safer, greener and more pedestrian-friendly campus.

Thank you for your understanding and cooperation.